Changi Water Reclamation Plant
Retrofit two existing bioreactor basins with two membrane plants (polymeric and ceramic); install new headworks fine screens, washer, and compactor system; construct a new chemical unloading facility, chemical storage and dosing facility for four chemicals; and add high-pressure pumping system, chilled-water pumping system, cooling-water system for effluent pumps, install new strain-press facility. Civil and structural engineering works are also included.
Modification and Diversion of live plant operation; Supply, deliver, install, test and commission other equipment such as Mixers, Penstocks, Bubble Diffuser assembly, VFD motors, Compressed Air system, Lifting equipment, 22kV/415V Transformers, LV Switchboards, MCC, AHF, Distribution Boards, LCC, 22kV Cables, LV power and control cables, Earthing, lighting protection system, lightnings, SCADA, Communication Network, PLC, UPS, LCP and NFI Panels, Field Instrumentation, Control and Monitoring Software, and Building Services. Provide operation and maintenance services upon completion of construction.