Ulu Pandan - Biogas

Ulu Pandan - Biogas Generators

-Design and construct, test and commission new containerised two (2) numbers of 2MW GEGs , its connecting pipelines and ancillary equipment.
-Provide operation and maintenance services for the new GEGs and its ancillaries commencing
For Civil works - The provision of all materials, construction plant and equipment.
For Mechanical Works – Design, procurement, installation, testing and commissioning of all plant and equipment required for the installation of GEGs to produce electricity from biogas
For Electrical Works – The detailed design, procurement, installation, testing and commissioning of all electrical equipment

Challenge

Share by: